Increase Profits with a Production Planning Scheduler

~Introduction to the Production Scheduling System Asprova~

Chapter 06 - Structure and Effects of the APS System

Production Scheduling

Q: What is the sequence for production scheduling?

A: The order in which production scheduling is done would be as follows.

1)  Input the BOM (bill of materials).
2)   Input the manufacturing order.
3)  Refer to the BOM, develop the manufacturing order process and build the network.
4)  In the sequence in which work is specified by planning parameters, allocate each resources based on the BOM.

030.jpg

The method of allocation in 4) has already been explained, it is theory of constraints scheduling. It takes the load of all materials in the plant (machinery, personnel, tool) into consideration and allocates the jobs to the resources. The result is to allocate all work by theory of constraints to resources making a production schedule that reduces production lead-time.

Related articles : 

Birth of the Advanced Planning and Scheduling System (APS)

Visualizing the BOM (Bill of Materials)

Backward Scheduling for Theory of Constraints (JIT Scheduling)

Forward Scheduling for Theory of constraints

Next Scheduling Orders

Previous A Mixture of MTO and MTS Production

production_planning_scheduling_book.jpg